Abstract
A new model to evaluate the plant availability of a fusion reactor by considering the required cooling time before starting the scheduled replacement of in-vessel components was developed and incorporated in the tokamak system design code TPC-SCONE. Plant availability strongly depends on the electric output and decreases with increasing electric output. The plant availability does not much improve by advances in the physics or engineering design conditions. Consequently, the effect of the increase in the electric output on reducing the cost of electricity is diminished. Thus, proper selection of the electric output of a fusion reactor (especially for a DEMO reactor) is likely required to achieve the plant availability target.
Original language | English |
---|---|
Article number | 3405140 |
Journal | Plasma and Fusion Research |
Volume | 9 |
Issue number | SpecialIssue2 |
DOIs | |
Publication status | Published - 2014 |
Externally published | Yes |
Keywords
- Cost model
- Plant availability
- Reactor design
- System design code
- Time required for replacement
ASJC Scopus subject areas
- Condensed Matter Physics